최신 Autodesk Certified Professional BIM_MGT_101 무료샘플문제:
1. A BIM manager is reviewing a consultant's architectural model before the next coordination milestone. The project requires each model to conform to a defined naming convention, include COBie parameters, and populate shared parameters according to the Model Element Table. The BIM manager notices that several elements are missing metadata and that some naming is inconsistent.
Which step best supports a systematic evaluation of completeness and compliance with project standards?
A) Filter out incomplete elements in a 3D view and hide them to avoid confusion during coordination.
B) Ask the design team to re-export the model with updated information based on verbal clarification and metadata from the BIM Execution Plan.
C) Manually review each element in the Model Browser to confirm naming and parameter completeness.
D) Use a model checker or data-validation tool to compare parameter presence, naming conventions, and required values against the established project standard.
2. The BIM manager is coordinating a multi-building project in which each building must maintain a unique internal coordinate system but share a common origin point for site-wide references.
Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)
A) Assign a unique Project Base Point for each building model.
B) Share coordinates by acquiring from the master site model, using a single Survey and Project Base Point.
C) Place the Survey Point at the shared site origin for all buildings.
D) Place the Project Base Point at the shared site origin for all buildings.
E) Create unique Survey and Project Base Points for all buildings, maintaining individual Building Coordination.
3. A government facility project requires unique data formatting and export requirements that comply with a global data-management initiative. A workflow utilizing a newly released add-on tool is developed to perform this task.
How should a BIM manager define training and ensure the appropriate staff receive it?
A) Develop a full training curriculum and assign all members of the project team, regardless of role.
B) Create training tutorials for the unique tasks and assign them to the members whose roles are responsible for the tasks.
C) Assign the task to the team and provide training to any user whose Journal reveals a crash.
D) Review each project model at milestone deliveries and assign the team training on items that fail the quality-control review.
4. During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model's file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.
What is the most likely root cause of the model performance degradation?
A) A rise in geometry complexity.
B) An accumulation of audit history and backup data.
C) The increase in model warnings.
D) The presence of imported Civil CAD files.
5. During a project onboarding meeting, the client provides their current BIM standards and templates to the BIM manager. The project will involve multiple consultants across different regions and is being delivered under a fast-track schedule with a high volume of design iterations. The client has also indicated that they plan to use a new collaboration platform not previously piloted on similar project types.
The BIM manager must evaluate whether the client's materials are sufficient and aligned with digital-delivery expectations, collaboration goals, and coordination requirements.
Given these factors, which two of the client's BIM resources must be prioritized for review to evaluate their ability to support digital delivery and coordination across regions, teams, and time constraints? (Select two.)
A) Confirm that shared-parameter files and naming conventions are consistent across provided templates and documentation to support data consistency.
B) Review previous projects' sample sheets and title blocks to assess the visual style preferred by the client.
C) Review the provided project templates to confirm whether units, naming conventions, and view organization are consistent and support coordination.
D) Confirm whether the templates allow full customization by each discipline so teams can adapt the setup to their own preferences.
E) Prioritize identifying which users from the client's team will need Revit training or software access before the project begins.
질문과 대답:
| 질문 # 1 정답: D | 질문 # 2 정답: A,C | 질문 # 3 정답: B | 질문 # 4 정답: D | 질문 # 5 정답: A,C |














0 개 고객 리뷰
품질과 가치ITCertKR 의 높은 정확도를 보장하는 최고품질의 덤프는 IT인증시험에 대비하여 제작된것으로서 높은 적중율을 자랑하고 있습니다.
테스트 및 승인ITCertKR 의 덤프는 모두 엘리트한 전문가들이 실제시험문제를 분석하여 답을 작성한 만큼 시험문제의 적중률은 아주 높습니다.
쉽게 시험패스ITCertKR의 테스트 엔진을 사용하여 시험을 준비한다는것은 첫 번째 시도에서 인증시험 패스성공을 의미합니다.
주문하기전 체험ITCertKR의 각 제품은 무료 데모를 제공합니다. 구입하기로 결정하기 전에 덤프샘플문제로 덤프품질과 실용성을 검증할수 있습니다.