최신 TS 070-178 무료샘플문제:
1. You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You identify an available resource. You need to assign the task to the resource without scheduling the task. What should you do?
A) Use the Calendar view.
B) Use the Team Planner view.
C) Use the Replace feature in the Assign Resources dialog box.
D) Use the Add Resources function.
2. You need to view Task ID 0 on your project plan. What should you do?
A) Insert a new Summary Task.
B) On the Advanced tab of the Project 2010 options, select Show Status Bar.
C) On the Format tab, select Summary Tasks.
D) On the Format tab, select Project Summary Task.
3. You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?
A) Click New Tasks and change the option to Auto Scheduled.
B) Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.
C) On the Schedule tab of the Project options, change the New tasks created option to Manually Scheduled.
D) On the Display tab of the Project options, clear the Edits to start and finish dates check box.
E) On the Advanced tab of the Project options, clear the Automatically add new resources and tasks check box.
4. You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically. How should you configure Task 2?
A) Set the schedule mode to Manually Scheduled.
B) Set the constraint type to Start No Earlier Than.
C) Set the task type to Fixed Duration.
D) Set the lag to two elapsed days (2ed).
5. You need to compare the total work of your project's deliverables against the baseline work. What should you do?
A) From the Task Sheet view, change the table to display the Summary table.
B) From the Gantt Chart view, change the table to display the Work table.
C) Use the Task Usage view and the Task Form in the details pane.
D) Use the Tracking Gantt view and display the default Entry table.
질문과 대답:
| 질문 # 1 정답: B | 질문 # 2 정답: D | 질문 # 3 정답: C | 질문 # 4 정답: B | 질문 # 5 정답: B |














1215 개 고객 리뷰
품질과 가치ITCertKR 의 높은 정확도를 보장하는 최고품질의 덤프는 IT인증시험에 대비하여 제작된것으로서 높은 적중율을 자랑하고 있습니다.
테스트 및 승인ITCertKR 의 덤프는 모두 엘리트한 전문가들이 실제시험문제를 분석하여 답을 작성한 만큼 시험문제의 적중률은 아주 높습니다.
쉽게 시험패스ITCertKR의 테스트 엔진을 사용하여 시험을 준비한다는것은 첫 번째 시도에서 인증시험 패스성공을 의미합니다.
주문하기전 체험ITCertKR의 각 제품은 무료 데모를 제공합니다. 구입하기로 결정하기 전에 덤프샘플문제로 덤프품질과 실용성을 검증할수 있습니다.